PRODUCTION PROCESS
COMPLEMENTARY FORESTRY PRODUCTS
DEVELOPMENT PROGRAMME
RESPONSIBLE ENVIRONMENTAL MANAGEMENT
CONTACT
UPM INFORME PĂBLICO
THE TIMBER SUPPLY PROCESS CONTINUED as we prepare for the start of operations at the UPM mill in Paso de los Toros. In harvesting, 2021 was a year of preparing and planning for increased activities. In this sense, we strongly focused on the development of programmes for new contractors that were selected after an open call.
Blanquillo, La Paloma and Villa del Carmen. At the end of 2021, around 250 people participated. In company owned harvesting operations, we renewed the machinery on the Second Front to incorporate the latest technology available globally in harvesting (Harvester) and extraction (Forwarder).
until each company begins to operate. Looking at the regional development of the central and northern areas, which will stock the Paso de los Toros mill with timber, the companies that supply the harvesting machinery held informative talks and courses for operators in different communities in the interior, such as Fraile Muerto, San Gregorio de Polanco,
During 2021, all new harvesting contractors took part in an induction programme developed by UPM to teach them about the safety and operational standards they must comply with in order to begin operations. The programme includes training, work plans, on-site visits, among others. The programme will continue through 2022
AVERAGE YIELD (m 3 /ha.)
TOTAL HARVEST (thousands of m 3 )
SPECIES
TOTAL
COASTAL NORTHERN SOUTH-CENTRAL REGION REGION REGION
Eucalyptus
3,629
E.grandis
24-32
26-34
22-28
Pinus
448
E.dunnii
20-28
24-30
22-26
Total
4,077
E.maidenii
15-20
16-20
16-20
E.globulus
07-12
07-11
11-16
E.viminalis
15-20
15-20
18-24
Pinus sp.
12-16
15-20
12-18
E.tereticornis/E.camaldulensis
10-14
11-15
8-12
E.benthamii
22-28
25-30
22-26